History & communities

When Libby Dam was built and Lake Koocanusa filled

The Libby Dam timeline from construction in 1966 through impoundment, first full pool, first generator service and the August 1975 dedication.

Construction began in 1966. The Corps began filling Lake Koocanusa on March 21, 1972, finished the dam structure in July 1973 and first reached full pool in July 1974. The project was dedicated on August 24, 1975.

How filling and construction overlapped

The Corps’ water control manual dates the first large concrete pour to June 1, 1968. Its chronology shows that work on the structure continued after the first reservoir rise. That is why 1972 appears in histories of when Lake Koocanusa formed, while 1973 appears as the dam’s construction completion year.

The first full pool followed on July 29, 1974, according to the Corps’ timeline. The U.S. Geological Survey’s early study of reservoir nutrients and productivity also dates impoundment to March 21, 1972. Its measurements document a lake still changing in the years after it was formed.

Power and public dedication

The first generating unit entered service in August 1975. President Gerald Ford took part in the dedication on August 24, and the Corps used that anniversary for its 2025 commemoration. The water control manual records other generators coming online in stages after the dedication, including Unit 5 in December 1984. Use the date that matches the event you are describing.